|
|
|
|
|
|
|
|
|
|
|
|
October, 2021
|
|
|
|
September, 2021
24th thru 30th Street opened on April 2, 2021
2/16/21 access to Beachwalk on 25th Street:
Photos taken on February 8, 2021, with views from 41st to 43rd street:
The original projected completion date for the Beachwalk Project was originally on February 13, 2021 (as seen in GO Bond Project Status Report below.) The new projected completion date is June, 2021.
|
4/21/21 - 41-42nd street circles:
Information on Final Phase of Beachwalk:
53rd thru 64th Street Section was open on December 18, 2019.
|
Below are the responses submitted via email:
Signs need to be placed in locations that are visible. Many of them are facing in the wrong direction and/or too far to be seen.
These signs are either too tall or placed too far from the Beachwalk which makes them very difficult to see:
We're advocating for "Block Signage" throughout:
|
Beachwalk Phase I - Ribbon Cutting CeremonyJune 13, 2019
|